Pollution Consent Delayed? What the 2026 Guidelines Say

Industrial units seeking Consent to Establish (CTE) or Consent to Operate (CTO) are subject to prescribed processing timelines under the national consent guidelines.

The original Control of Water Pollution (Grant, Refusal or Cancellation of Consent) Guidelines, 2025, prescribed maximum timelines for consent applications.

If the State Pollution Control Board or Pollution Control Committee failed to decide an application within the applicable period, the case could be placed before the State Level Monitoring Committee (SLMC) for disposal.

What Changed in 2026?

The 2026 amendment, G.S.R. 63(E), dated 23 January 2026, changed several provisions of the 2025 framework, including the processing timelines for consent applications.

Current Processing Timelines

ConsentRedOrangeGreen
CTE – ordinary application60 days45 days30 days
CTO – first grant90 days60 days30 days
CTO – expansion/amendment90 days60 days30 days

What If the Consent Is Delayed?

The 2025 framework provides for escalation to the State Level Monitoring Committee (SLMC) where the SPCB/PCC does not grant or refuse consent within the prescribed timeline.

The Committee shall dispose of the application within 30 days from the date of its receipt. It must examine the reasons for the delay and may recommend appropriate disciplinary action where the delay is not justified. The State Board is required to comply with the Committee’s decision.

The Committee may also recommend that the case be presented for contravention of the Act before the concerned adjudicating officer under Section 45B of the Water Act.

The 2026 amendment also introduces deemed CTE for eligible Micro and Small units located in duly notified industrial estates or industrial areas, subject to submission of the prescribed self-certified Form-I. It also makes Consent to Operate perpetual once granted.

Note: The 2026 amendment removes the words “or refusal” from the CTE timeline provision. The amendment does not expressly state that Pollution Control Boards cannot refuse CTE applications, so the position on refusal remains unclear.

Updates:
1. Tamil Nadu sets 21-day deadline for industrial clearances, deemed approval if delayed

Last reviewed: 16 November 2026.